Friday, May 24, 2013   
  Search   
 

Office 2010 - Launch Event

Register  Login  
Forums  
     Minimize  

MeraWindows Forums - Get your Computer Problems Fixed

This is a site run by the community - for the community. At the site, we share and contribute our computer learnings with each other. We discuss about Windows, Office, Mobile, Gaming and other computer related topics. At our forums you can post your queries and our very helpful community members will respond quickly to your queries. We organize lots of competitions from time to time and award prizes to the winners.
You will need to register at the site before posting in forums. It's absolutely free. After registering, you can get all the benefits available to our registered members, you can access our Downloads section, you can participate in contests, etc. You can post in forums in English as well as in Hindi, in fact we encourage you to use Hindi in your posts. If you have any problem with registration or login, please contact us.

     
  
HomeHomeMicrosoft Offic...Microsoft Offic...Microsoft Proje...Microsoft Proje...Nonworking daysNonworking days
Previous
 
Next
New Post
1/15/2009 3:25 PM
 

Hi all,

How I can set alternate Sat/Sun (2nd,4th) as nonworking days for a year in calendar?

 

Deepali Joshi

 
New Post
1/27/2009 3:13 PM
 

Hi Deepali

In my view it is not possible by a direct command. In Tools > Change working time first create a calendar for the required year with all Saturdays working. Then in 'Exceptions' for that period, you will have to select alternate Staurdays and designate as holidays.

I hope it helps.

Vanita Ahuja

 

 
New Post
3/16/2009 1:44 PM
 

HI Deepali

Thankyou for posting your query in merawindows.

It would be nice if you also mention the version of MS Project being used in you query.

In order to set alternate saturday/sunday as non working days in MS Project 2007 please follow these steps:

  1. From the Tools menu choose Change working time
  2. Click on any one of second saturday in the calendar interface
  3. Give it some name in the Exception "Second Saturday"
  4. Click on Details
  5. Mark it as non working
  6. In the recurrence pattern choose Monthly, Second saturday of every month.
  7. Give a relavant end by date
  8. Now all second saturdays will be marked as non working
  9. like wise create exceptions for fourth saturday and sunday

If you are using MS Project 2003 you will have to set each alternate saturday/sunday as non working manually.

Please let me know if it works for you.

 

Thanks

Manmeet

MVP-Project

 
New Post
4/13/2009 3:20 PM
 

Hi Manmeet,

Thanks for your help.

When you give any solution it realy work.

regards

Sajid

 

 

 

 
New Post
4/13/2009 3:23 PM
 

Hi Manmeet,

Thanks for your help

Regards,

Sajid

 
New Post
4/22/2009 11:55 AM
 

Your welcome Sajid.

 

 

Regards

Manmeet

 
New Post
9/19/2012 12:06 AM
 
Thanks Manmeet. I was searching for the solution for quite long time. You steps helps me out. Thanks
 